3 Jan
2008
3 Jan
'08
6:29 a.m.
On Thu, Jan 03, 2008 at 10:52:07AM +0900, Everett, Vernon wrote:
Hobbit has a beautiful facility to calculate uptime stats. But PHBs, being what they are, want more. Is there a way to flag an outage as "scheduled" or similar, and not include it in the uptime stats calculation?
There is, but you have to do it in advance: By disabling the host or status that is planned to be down.
It would be good to be able to flag the scheduled outage as "not a real outage" after the fact, because during the outage, we use Hobbit to keep tabs on what goes down and comes up and when.
I know, I've had the same request from my own users.
Henrik