Hi Mike,
On Thu, 31 Oct 2013, Mike Burger wrote:
We have maintenance scheduled for 14 servers in our environment this Saturday night. Knowing that the systems could be rebooted, etc, anytime between 9PM and 1AM, I've prescheduled these servers to be "disabled" from 2059 on Saturday night thru 0101 on Sunday morning.
I'm now being given a directive to have these systems disabled from 1959 to 0101.
I'd like to be able to modify the existing schedule, without having to remove and recreate them. As the GUI doesn't provide this option (only an option to cancel), I'm hoping that I can find a file wherein I can modify the schedule.
Unless I am missing something it is as simple going into the gui and disabling them again with the correct schedule. I have done that many times. Last change wins.
Regards,
-- Tom me at tdiehl.org Spamtrap address me123 at tdiehl.org